BUILDING UPGRADES

REFURBISHMENT OF HARTEL S.A. MAIN PRODUCTION HALL


Project Owner: HARTEL S.A.
Location: Kalohori, Thessaloniki
Year of project completion: 2000
Surface area: 690m2

The premises of Hartel S.A. -Paper and cardboard boxes factory- in Kalohori Thessaloniki were built in the mid 1980's. In 2000, under the reorganization of the main production hall of 4.245 m2 area, Hercon undertook the design and construction of a project which included the addition of an extension building of 700 m2 and the upgrading of facades in conjunction with the insulation of the building shell.
At the same time an additional independent metal building of 400 m2 with a parabolic roof was constructed.
The architectural designs were carried out by architect Costas Antoniou. The final result was a renovated high aesthetic building that covers all current company needs.